Dept. of Trans. PROGRESS Serial No. Contract No. 23-321-18-27 04-160304 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 79% Location: Federal Project: 04-ALA-84-13.0/13.6 ACNH-P084(54) Progress payment No. 033 Payment period ending: 11-20-23 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,819,441.40 169,925.65 2. a. Extra Work 2,039,093.01 0.00 b. Adustment Comp. 379,233.32 0.00 3. Materials on Hand 74,058.66 3,000.00 4. Earned Subject to Retention 17,311,826.39 172,925.65 5. Mobilization 1,740,000.00 0.00 6. Total Work Completed 18,977,767.73 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,051,826.39 172,925.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 172,925.65