Dept. of Trans. PROGRESS Serial No. Contract No. 06-020-07-44 04-162004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 50% 04-ALA-580-45.8/46.9 Federal Project: ER-1597(4) Progress payment No. 06 Payment period ending: 01-20-06 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,240,988.31 618,564.68 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 229,509.14 -267,515.42 4. Earned Subject to Retention 4,470,497.45 351,049.26 5. Mobilization 700,000.00 0.00 6. Total Work Completed 4,940,988.31 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,170,497.45 351,049.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 351,049.26