Dept. of Trans. PROGRESS Serial No. Contract No. 03-051-12-02 04-163624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 72% 04-MRN-101-0.9/1.1 Federal Project: 04-SF-280-R2.7/R2.8 ACIM-280-1(103) ACNH-P101(994) Progress payment No. 06 Payment period ending: 02-20-03 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 958231430 Escrow No. 02014 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,178,142.00 638,407.38 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 64,752.36 -194,257.09 4. Earned Subject to Retention 1,242,894.36 444,150.29 5. Mobilization 6. Total Work Completed 1,178,142.00 7. Deductions 8. a.Contract Retentions -62,144.72 -22,207.52 b. Unsatisfactory Prog. 0.00 23,026.94 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,180,749.64 444,969.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 444,969.71