Dept. of Trans. PROGRESS Serial No. Contract No. 03-108-12-36 04-163624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 85% 04-MRN-101-0.9/1.1 Federal Project: 04-SF-280-R2.7/R2.8 ACIM-280-1(103) ACNH-P101(994) Progress payment No. 08 Payment period ending: 04-20-03 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 958231430 Escrow No. 02014 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,556,900.15 300,934.57 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 51,375.20 -64,752.36 4. Earned Subject to Retention 1,608,275.35 236,182.21 5. Mobilization 6. Total Work Completed 1,556,900.15 7. Deductions 8. a.Contract Retentions -80,413.77 -11,809.11 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,527,861.58 224,373.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 224,373.10