Dept. of Trans. PROGRESS Serial No. Contract No. 03-140-12-44 04-163624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 70% 04-MRN-101-0.9/1.1 Federal Project: 04-SF-280-R2.7/R2.8 ACIM-280-1(103) ACNH-P101(994) Progress payment No. 09 Payment period ending: 05-20-03 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 958231430 Escrow No. 02014 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,638,633.31 81,733.16 2.a. Extra Work 9,320.76 9,320.76 b. Adjustment Comp. -12,493.01 -12,493.01 3. Materials on Hand 25,687.60 -25,687.60 4. Earned Subject to Retention 1,661,148.66 52,873.31 5. Mobilization 6. Total Work Completed 1,635,461.06 7. Deductions 8. a.Contract Retentions -83,057.43 -2,643.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,578,091.23 50,229.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,229.65