Dept. of Trans. PROGRESS Serial No. Contract No. 03-171-15-43 04-163624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 80% 04-MRN-101-0.9/1.1 Federal Project: 04-SF-280-R2.7/R2.8 ACIM-280-1(103) ACNH-P101(994) Progress payment No. 10 Payment period ending: 06-20-03 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 958231430 Escrow No. 02014 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,741,635.24 103,001.93 2.a. Extra Work 9,320.76 0.00 b. Adjustment Comp. -12,493.01 0.00 3. Materials on Hand 0.00 -25,687.60 4. Earned Subject to Retention 1,738,462.99 77,314.33 5. Mobilization 6. Total Work Completed 1,738,462.99 7. Deductions 8. a.Contract Retentions -86,923.15 -3,865.72 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,651,539.84 73,448.61 10. Reduction Amt to Escrow 11. Payment to Escrow 86,920.00 12. Net Pymt. this Estimate 73,448.61