Dept. of Trans. PROGRESS Serial No. Contract No. 10-300-10-15 04-163734 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 45% 04-SF-101-9.2/9.8 Federal Project: 04-SF-1-6.8/7.1 ACBR-X075(27) NH-X075(27) Progress payment No. 11 Payment period ending: 10-20-10 C C MYERS INC ALTERNATIVE A P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,699,199.43 1,513,230.70 2.a. Extra Work 7,408,448.45 40,832.78 b. Adjustment Comp. 3. Materials on Hand 1,168,503.13 582,102.68 4. Earned Subject to Retention 29,276,151.01 2,136,166.16 5. Mobilization 3,521,256.00 0.00 6. Total Work Completed 31,628,903.88 7. Deductions -22,129.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,775,278.01 2,136,166.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,136,166.16