Dept. of Trans. FINAL Serial No. Contract No. 15-313-14-07 04-163744 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SF-101-8.8/9.2 SARR-Q101(153) A-Q101(153) Progress payment No. 036 Payment period ending: 06-24-13 R AND L BROSAMER INC 1390 WILLOW PASS ROAD STE 950 CONCORD, CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,775,289.50 0.00 2. a. Extra Work 27,136,500.40 17,017.36 b. Adustment Comp. 31,710,603.07 0.00 3. Materials on Hand 4. Earned Subject to Retention 106,622,392.97 17,017.36 5. Mobilization 5,600,000.00 0.00 6. Total Work Completed 112,222,392.97 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 112,222,392.97 17,017.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,017.36