Dept. of Trans. PROGRESS Serial No. Contract No. 12-293-10-11 04-1637K4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 100% 04-SF-1-6.9/ .0 Federal Project: NH-X075(35) Progress payment No. 06 Payment period ending: 10-20-12 MAGGIORA & GHILOTTI INC 555 DUBOIS STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 355,364.00 0.00 2.a. Extra Work 111,629.31 69,194.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 466,993.31 69,194.00 5. Mobilization 6. Total Work Completed 466,993.31 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 466,993.31 69,194.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,194.00