Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-187-11-22 04-1637N4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SF-101-9.0 NHP-X075(45) Progress payment No. 005 Payment period ending: 03-01-16 POWER ENGINEERING CONSTRUCTION CO 1501 VIKING ST #200 ALAMEDA CA 94501 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,256,219.84 0.00 2. a. Extra Work 216,036.37 24,776.61 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,472,256.21 24,776.61 5. Mobilization 160,000.00 0.00 6. Total Work Completed 2,632,256.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,632,256.21 24,776.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,776.61