Dept. of Trans. PROGRESS Serial No. Contract No. 06-356-08-49 04-165944 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 69% 04-SCL-85-R20.0/R22.0 Federal Project: 04-SCL-82-18.7/19.0 NONE Progress payment No. 08 Payment period ending: 12-20-06 AMLAND 3168 KNIGHTS BRIDGE RD SAN JOSE CA 95132 Escrow No. 02229 Total Estimate This Estimate 1. Contract Itms Without Mobil. 572,450.13 211,780.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 29,406.12 29,406.12 4. Earned Subject to Retention 601,856.25 241,186.12 5. Mobilization 152,000.00 0.00 6. Total Work Completed 724,450.13 7. Deductions -27,000.00 0.00 8. a.Contract Retentions -32,107.53 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 694,748.72 241,186.12 10. Reduction Amt to Escrow 11. Payment to Escrow 32,100.00 12. Net Pymt. this Estimate 241,186.12