Dept. of Trans. PROGRESS Serial No. Contract No. 06-048-13-41 04-171204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 77% 04-SF-101-6.7/8.0 Federal Project: ACST-Q101(86) PHG-Q101(86) Progress payment No. 07 Payment period ending: 02-20-06 W BRADLEY ELECTRIC INC 90 HILL ROAD NOVATO CA 94945 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 500,415.00 129,915.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 139,447.15 -19,936.00 4. Earned Subject to Retention 639,862.15 109,979.00 5. Mobilization 96,900.00 0.00 6. Total Work Completed 597,315.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -16,222.00 -10,997.90 c. Reduction after 95% Comp. 9. Total pay to Contractor 720,540.15 98,981.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 98,981.10