Dept. of Trans. PROGRESS Serial No. Contract No. 17-114-16-41 04-172454 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 30% Location: Federal Project: 04-ALA-880-18.4/18.4 IM Progress payment No. 013 Payment period ending: 04-20-17 JOHN SEMSEN LANDSCAPING CO 21161 LYONS BALD MNT RD SONORA CA 95370 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 339,484.92 2,079.00 2. a. Extra Work 7,700.00 0.00 b. Adustment Comp. 11,621.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 358,806.42 2,079.00 5. Mobilization 44,000.00 0.00 6. Total Work Completed 402,806.42 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 402,806.42 2,079.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,079.00