Dept. of Trans. PROGRESS Serial No. Contract No. 11-168-15-58 04-174414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 0% 04-ALA-84-12.1/13.3 Federal Project: HSST-P084(37) P-P084(37) Progress payment No. 04 Payment period ending: 06-20-11 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 119,784.75 66,575.75 2.a. Extra Work 68,036.74 20,896.65 b. Adjustment Comp. 3. Materials on Hand 364,914.45 114,712.50 4. Earned Subject to Retention 552,735.94 202,184.90 5. Mobilization 280,000.00 0.00 6. Total Work Completed 467,821.49 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 832,735.94 202,184.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 202,184.90