Dept. of Trans. PROGRESS Serial No. Contract No. 07-263-10-39 04-174934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 35% 04-SCL-152-19.7/21.3 Federal Project: HP21-5204(61) L-5204(61) Progress payment No. 03 Payment period ending: 09-20-07 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,485,385.59 697,727.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 40,112.80 -72,801.61 4. Earned Subject to Retention 1,525,498.39 624,925.39 5. Mobilization 647,250.00 0.00 6. Total Work Completed 2,132,635.59 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,172,748.39 624,925.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 624,925.39