Dept. of Trans. PROGRESS Serial No. Contract No. 09-294-15-20 04-177904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 64% 04-ALA-880-28.2/28.5 Federal Project: SARR-880-1(58) A-880-1(58) Progress payment No. 02 Payment period ending: 10-20-09 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,560,591.00 1,821,426.00 2.a. Extra Work 93,100.00 93,100.00 b. Adjustment Comp. 544,900.05 544,900.05 3. Materials on Hand 4. Earned Subject to Retention 3,198,591.05 2,459,426.05 5. Mobilization 617,500.00 130,000.00 6. Total Work Completed 3,816,091.05 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,816,091.05 2,589,426.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,589,426.05