Dept. of Trans. PROGRESS Serial No. Contract No. 01-022-07-12 04-181404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 33% 04-ALA-80-7.4/8.0 Federal Project: ACIM-080-1(80) Progress payment No. 03 Payment period ending: 01-20-01 BENCO CONTRACTING AND ENGINEERING INC 9888 KENT STREET ELK GROVE CA 95624 Escrow No. 01593 Total Estimate This Estimate 1. Contract Itms Without Mobil. 217,366.50 84,446.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 217,366.50 84,446.50 5. Mobilization 47,500.00 10,000.00 6. Total Work Completed 264,866.50 7. Deductions 8. a.Contract Retentions -15,368.30 -2,076.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 249,498.20 92,370.20 10. Reduction Amt to Escrow 11. Payment to Escrow 15,360.00 12. Net Pymt. this Estimate 92,370.20