Dept. of Trans. PROGRESS Serial No. Contract No. 01-292-11-44 04-181404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 85% 04-ALA-80-7.4/8.0 Federal Project: ACIM-080-1(80) Progress payment No. 11 Payment period ending: 10-19-01 BENCO BRIDGES 9888 KENT STREET ELK GROVE CA 95624 Escrow No. 01593 Total Estimate This Estimate 1. Contract Itms Without Mobil. 674,837.20 20,000.00 2.a. Extra Work 86,310.08 733.64 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 761,147.28 20,733.64 5. Mobilization 50,000.00 0.00 6. Total Work Completed 811,147.28 7. Deductions 8. a.Contract Retentions -38,057.36 -1,036.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 773,089.92 19,696.96 10. Reduction Amt to Escrow 11. Payment to Escrow 38,050.00 12. Net Pymt. this Estimate 19,696.96