Dept. of Trans. PROGRESS Serial No. Contract No. 02-018-12-13 04-181404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 95% 04-ALA-80-7.4/8.0 Federal Project: ACIM-080-1(80) Progress payment No. 14 Payment period ending: 01-20-02 BENCO BRIDGES 9888 KENT STREET ELK GROVE CA 95624 Escrow No. 01593 Total Estimate This Estimate 1. Contract Itms Without Mobil. 709,007.20 0.00 2.a. Extra Work 92,987.05 1,092.50 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 801,994.25 1,092.50 5. Mobilization 50,000.00 0.00 6. Total Work Completed 851,994.25 7. Deductions 8. a.Contract Retentions -40,099.71 -54.62 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 811,894.54 1,037.88 10. Reduction Amt to Escrow 11. Payment to Escrow 40,040.00 12. Net Pymt. this Estimate 1,037.88