Dept. of Trans. PROGRESS Serial No. Contract No. 03-232-12-36 04-181624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 38% 04-ALA-80-5.7/6.8 Federal Project: ACIM-080-1(86) Progress payment No. 24 Payment period ending: 08-20-03 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 94901 Escrow No. 01858 Total Estimate This Estimate 1. Contract Itms Without Mobil. 688,523.10 5,893.10 2.a. Extra Work 36,561.43 0.00 b. Adjustment Comp. 6,904.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 731,988.53 5,893.10 5. Mobilization 93,000.00 0.00 6. Total Work Completed 824,988.53 7. Deductions 8. a.Contract Retentions -36,599.43 -294.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 788,389.10 5,598.44 10. Reduction Amt to Escrow 11. Payment to Escrow 36,300.00 12. Net Pymt. this Estimate 5,598.44