Dept. of Trans. PROGRESS Serial No. Contract No. 08-081-08-57 04-1A0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 17% 04-SON-12-23.1/34.3 Federal Project: ACST-P012(99) PHG-P012(99) Progress payment No. 01 Payment period ending: 03-20-08 LINEAR OPTIONS INC 1 KELLY CT MENLO PARK CA 94025 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 116,744.00 116,744.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 116,744.00 116,744.00 5. Mobilization 61,750.00 61,750.00 6. Total Work Completed 178,494.00 7. Deductions -30,883.07 -30,883.07 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 147,610.93 147,610.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 147,610.93