Dept. of Trans. PROGRESS Serial No. Contract No. 07-325-10-24 04-1A0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 43% 04-SCL-82-23.2/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 11-20-07 PRISM ENGINEERING INC 630 REED ST SANTA CLARA CA 95050 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 257,914.50 123,435.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 257,914.50 123,435.00 5. Mobilization 30,000.00 1,500.00 6. Total Work Completed 287,914.50 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -12,895.73 -6,171.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 265,018.77 108,763.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,763.25