Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-291-10-41 04-1A2414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-980-1.3/2.0 Federal Project: 04-ALA-24-R1.8/R4.3 NONE Progress payment No. 03 Payment period ending: 10-08-10 COAST CONSTRUCTION INC 4460 REDWOOD HIGHWAY SUITE 16 SAN RAFAEL CA 94903 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 368,864.00 7,065.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 368,864.00 7,065.00 5. Mobilization 6. Total Work Completed 368,864.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 368,864.00 7,065.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,065.00