Dept. of Trans. PROGRESS Serial No. Contract No. 08-028-13-19 04-1A2804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 74% 04-SOL-12-26.4/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 01-20-08 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 575,038.04 82,500.00 2.a. Extra Work 65,524.98 65,524.98 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 640,563.02 148,024.98 5. Mobilization 40,000.00 0.00 6. Total Work Completed 680,563.02 7. Deductions 8. a.Contract Retentions -32,028.15 -7,401.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 648,534.87 140,623.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 140,623.73