Dept. of Trans. PROGRESS Serial No. Contract No. 17-080-11-32 04-1A2904 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 68% Location: Federal Project: 04-SON-12-9.6 STP-P012(113) Progress payment No. 029 Payment period ending: 03-20-17 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,351,952.91 278,000.00 2. a. Extra Work 320,476.05 -702.46 b. Adustment Comp. 746,382.76 0.00 3. Materials on Hand 36,958.09 -31,925.32 4. Earned Subject to Retention 7,455,769.81 245,372.22 5. Mobilization 560,000.00 0.00 6. Total Work Completed 7,978,811.72 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,015,769.81 245,372.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 245,372.22