Dept. of Trans. FINAL Serial No. Contract No. 19-052-07-09 04-1A2904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SON-12-9.6 STP-P012(113) Progress payment No. 047 Payment period ending: 10-25-18 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,894,156.44 0.00 2. a. Extra Work 435,613.11 -7,914.27 b. Adustment Comp. 746,382.76 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,076,152.31 -7,914.27 5. Mobilization 560,000.00 0.00 6. Total Work Completed 8,636,152.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,636,152.31 -7,914.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -7,914.27