Dept. of Trans. PROGRESS Serial No. Contract No. 07-166-14-21 04-1A3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 79% 04-SM-92-R9.4/R11.4 Federal Project: NONE Progress payment No. 02 Payment period ending: 06-20-07 OGRADY PAVING INC 2513 WYANDOTTE ST MOUNTAIN VIEW CA 94043 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 480,150.00 670.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 480,150.00 670.00 5. Mobilization 63,010.00 0.00 6. Total Work Completed 543,160.00 7. Deductions 8. a.Contract Retentions -24,007.50 -33.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 519,152.50 636.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 636.50