Dept. of Trans. PROGRESS Serial No. Contract No. 06-201-07-24 04-1A3804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 31% 04-SOL-0-0.0/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 07-20-06 RELIABLE TREE EXPERTS 2960 CHAPMAN STREET OAKLAND CA 94601 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 193,255.00 93,187.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 193,255.00 93,187.50 5. Mobilization 28,500.00 6,000.00 6. Total Work Completed 221,755.00 7. Deductions -24,150.00 -12,075.00 8. a.Contract Retentions -18,392.00 -8,385.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 179,213.00 78,727.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 78,727.25