Dept. of Trans. PROGRESS Serial No. Contract No. 10-111-09-55 04-1A4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 95% 04-ALA-24-R5.9/R6.2 Federal Project: 04-CC-24-R0.0/R0.5 NONE 04-ALA-260-R0.9/R1.9 Progress payment No. 11 Payment period ending: 04-20-10 TABER CONSTRUCTION P O BOX 1309 MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,550,100.00 2,534.00 2.a. Extra Work 183,292.58 85,215.00 b. Adjustment Comp. -200,035.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,533,357.58 87,749.00 5. Mobilization 6. Total Work Completed 2,533,357.58 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,533,357.58 87,749.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 87,749.00