Dept. of Trans. PROGRESS Serial No. Contract No. 09-327-08-01 04-1A5004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 72% 04-SM-0 Federal Project: ACHS-000C(308) NHG-000C(308) Progress payment No. 02 Payment period ending: 11-20-09 STATEWIDE SAFETY 130 GROBRIC COURT FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 543,696.00 381,435.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 543,696.00 381,435.00 5. Mobilization 60,000.00 3,000.00 6. Total Work Completed 603,696.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 603,696.00 384,435.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 384,435.00