Dept. of Trans. PROGRESS Serial No. Contract No. 11-171-07-24 04-1A5214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 55% 04-CC-160-0.8/1.3 Federal Project: 04-SAC-160-L0.0/L1.3 NONE Progress payment No. 12 Payment period ending: 06-20-11 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,920,720.07 1,662,680.22 2.a. Extra Work 206,299.93 14,286.06 b. Adjustment Comp. 1,162,400.98 127,400.40 3. Materials on Hand 813,056.11 -161,041.59 4. Earned Subject to Retention 22,102,477.09 1,643,325.09 5. Mobilization 3,400,000.00 0.00 6. Total Work Completed 24,689,420.98 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,502,477.09 1,643,325.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,643,325.09