Dept. of Trans. PROGRESS Serial No. Contract No. 12-325-10-35 04-1A5224 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 85% 04-SM-84-R29.0/R30.2 Federal Project: 04-ALA-84-R0.0/R1.2 NH Progress payment No. 28 Payment period ending: 11-20-12 SHIMMICK CONSTRUCTION COMPANY INC 8201 EDGEWATER DRIVE SUITE 20 OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,146,364.00 1,774,816.00 2.a. Extra Work 4,563,058.44 407,835.39 b. Adjustment Comp. 8,350,781.41 190,694.72 3. Materials on Hand 12,750.00 -352,265.00 4. Earned Subject to Retention 54,072,953.85 2,021,081.11 5. Mobilization 2,500,000.00 0.00 6. Total Work Completed 56,560,203.85 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 56,572,953.85 2,021,081.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,021,081.11