Dept. of Trans. PROGRESS Serial No. Contract No. 08-295-08-42 04-1A6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 33% 04-SON-101-2.4/R50.0 Federal Project: ACNH-Q101(140) G-Q101(140) Progress payment No. 02 Payment period ending: 10-20-08 CENTRAL FENCE CO 148 OTTO CIRCLE SACRAMENTO CA 95822 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 493,277.15 195,438.62 2.a. Extra Work 95,680.00 95,680.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 588,957.15 291,118.62 5. Mobilization 14,250.00 3,000.00 6. Total Work Completed 603,207.15 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 603,207.15 294,118.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 294,118.62