Dept. of Trans. PROGRESS Serial No. Contract No. 21-081-12-00 04-1A6614 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 4% Location: Federal Project: 04-MRN-101-8.4/8.7 NONE Progress payment No. 002 Payment period ending: 03-20-21 DISNEY CONSTRUCTION INC 533 AIRPORT BLVD #120 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 208,959.00 125,499.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 208,959.00 125,499.00 5. Mobilization 6. Total Work Completed 208,959.00 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 198,959.00 115,499.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,499.00