Dept. of Trans. PROGRESS Serial No. Contract No. 14-238-12-11 04-1A6714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 70% 04-ALA-580-46.1/46.1 Federal Project: NHPI-580-1(58) Progress payment No. 04 Payment period ending: 08-20-14 BAY LINE CUTTING AND CORING INC 1635 4TH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,756,580.10 899,086.40 2.a. Extra Work 90,091.12 14,484.25 b. Adjustment Comp. 149,985.00 0.00 3. Materials on Hand 29,278.82 1,307.69 4. Earned Subject to Retention 3,025,935.04 914,878.34 5. Mobilization 64,383.00 0.00 6. Total Work Completed 3,061,039.22 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,090,318.04 914,878.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 914,878.34