Dept. of Trans. PROGRESS Serial No. Contract No. 06-293-07-39 04-1A9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 62% 04-SM-101-19.2/19.9 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-06 VANGUARD CONSTRUCTION 1010 THIRTY NINTH AVENUE OAKLAND CA 94601 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 300,575.00 229,600.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 300,575.00 229,600.00 5. Mobilization 30,000.00 7,500.00 6. Total Work Completed 330,575.00 7. Deductions 8. a.Contract Retentions -15,028.75 -7,931.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 315,546.25 229,168.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 229,168.75