Dept. of Trans. PROGRESS Serial No. Contract No. 06-201-07-24 04-1A9604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-MRN-101-0.1/0.2 Federal Project: NONE Progress payment No. 11 Payment period ending: 07-20-06 PAGNI CONSTRUCTION INC 1397 BIRDIE DRIVE WINDSOR CA 95492 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 307,602.80 3,056.20 2.a. Extra Work 81,255.38 33,478.50 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 388,858.18 36,534.70 5. Mobilization 39,694.00 0.00 6. Total Work Completed 428,552.18 7. Deductions -126.00 0.00 8. a.Contract Retentions -19,442.91 -1,826.74 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 408,983.27 34,707.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,707.96