Dept. of Trans. PROGRESS Serial No. Contract No. 11-297-14-01 04-1A9804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 57% 04-SCL-101-31.0/34.9 Federal Project: ARRA-Q101(164) L-Q101(164) HPLU-6204(90) Progress payment No. 11 Payment period ending: 10-20-11 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,363,130.99 636,694.90 2.a. Extra Work 181,704.94 34,968.35 b. Adjustment Comp. 68,603.00 68,603.00 3. Materials on Hand 255,892.15 255,892.15 4. Earned Subject to Retention 12,869,331.08 996,158.40 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 14,613,438.93 7. Deductions -2,649.93 -2,179.93 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,866,681.15 993,978.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 993,978.47