Dept. of Trans. PROGRESS Serial No. Contract No. 11-355-08-44 04-1A9804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 71% 04-SCL-101-31.0/34.9 Federal Project: ARRA-Q101(164) L-Q101(164) HPLU-6204(90) Progress payment No. 13 Payment period ending: 12-20-11 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,515,838.71 1,230,275.90 2.a. Extra Work 198,594.74 6,574.31 b. Adjustment Comp. 68,603.00 0.00 3. Materials on Hand 237,178.13 9,759.60 4. Earned Subject to Retention 15,020,214.58 1,246,609.81 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 16,783,036.45 7. Deductions -2,649.93 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,017,564.65 1,246,609.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,246,609.81