Dept. of Trans. PROGRESS Serial No. Contract No. 12-024-06-27 04-1A9804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 76% 04-SCL-101-31.0/34.9 Federal Project: ARRA-Q101(164) L-Q101(164) HPLU-6204(90) Progress payment No. 14 Payment period ending: 01-20-12 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,736,995.92 1,221,157.21 2.a. Extra Work 229,614.64 31,019.90 b. Adjustment Comp. 68,603.00 0.00 3. Materials on Hand 226,270.54 -10,907.59 4. Earned Subject to Retention 16,261,484.10 1,241,269.52 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 18,035,213.56 7. Deductions -2,649.93 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,258,834.17 1,241,269.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,241,269.52