Dept. of Trans. PROGRESS Serial No. Contract No. 20-142-10-10 04-1AA004 PROGRESS PAYMENT VOUCHER %complete: %time: 4% 58% Location: Federal Project: 04-SM-1-39.0/39.0 NONE Progress payment No. 005 Payment period ending: 05-22-20 MONTEREY MECHANICAL CO 8275 SAN LEANDRO ST OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 335,507.03 6,137.38 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 335,507.03 6,137.38 5. Mobilization 6. Total Work Completed 335,507.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 335,507.03 6,137.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,137.38