Dept. of Trans. PROGRESS Serial No. Contract No. 08-201-08-21 04-1E0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 30% 04-SM-101-6.6/11.9 Federal Project: NONE Progress payment No. 01 Payment period ending: 07-20-08 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 467,067.01 467,067.01 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 467,067.01 467,067.01 5. Mobilization 231,000.00 231,000.00 6. Total Work Completed 698,067.01 7. Deductions 8. a.Contract Retentions -46,706.70 -46,706.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 651,360.31 651,360.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 651,360.31