Dept. of Trans. PROGRESS Serial No. Contract No. 08-326-08-23 04-1E0804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 80% 04-CC-4-R40.8/48.4 Federal Project: NONE Progress payment No. 02 Payment period ending: 11-20-08 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 411,260.50 61,584.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 411,260.50 61,584.00 5. Mobilization 6. Total Work Completed 411,260.50 7. Deductions 8. a.Contract Retentions -20,563.03 -3,079.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 390,697.47 58,504.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,504.80