Dept. of Trans. PROGRESS Serial No. Contract No. 08-326-08-23 04-1E1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 83% 04-SOL-113-0.0/12.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 11-20-08 CENTRAL VALLEY ENGINERING AND ASPHALT INC 216 KENROY LANE ROSEVILLE CA 95678 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 500,287.04 94,309.74 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 500,287.04 94,309.74 5. Mobilization 6. Total Work Completed 500,287.04 7. Deductions 8. a.Contract Retentions -25,014.35 -4,715.48 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 475,272.69 89,594.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 89,594.26