Dept. of Trans. FINAL Serial No. Contract No. 10-313-09-44 04-1E2604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SM-92-0.0/3.2 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-23-10 G BORTOLOTTO AND COMPANY 582 BRAGATO ROAD SAN CARLOS CA 940706227 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 371,893.92 0.00 2.a. Extra Work 4,502.19 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 376,396.11 0.00 5. Mobilization 6. Total Work Completed 376,396.11 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 376,396.11 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00