Dept. of Trans. FINAL Serial No. Contract No. 11-258-11-17 04-1E2804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SON-101-29.4/R50.1 Federal Project: NONE Progress payment No. 04 Payment period ending: 02-16-11 PROFESSIONAL CONSTRUCTION SERVICES 4070 NELSON AVENUE SUITE A CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 394,812.21 0.00 2.a. Extra Work 35,032.45 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 429,844.66 0.00 5. Mobilization 6. Total Work Completed 429,844.66 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 429,844.66 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00