Dept. of Trans. PROGRESS Serial No. Contract No. 10-294-14-54 04-1E3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 53% 04-SF-101-3.4/8.3 Federal Project: 04-SF-280-R6.6/R0.6 ACBR-Q101(158) 04-MRN-101-7.4/R20.9 NH-Q101(158) Progress payment No. 02 Payment period ending: 10-20-10 BAY LINE CUTTING AND CORING INC 1033 YERBA BUENA AVENUE OAKLAND CA 94608 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 112,497.84 104,522.84 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 75,884.00 75,884.00 4. Earned Subject to Retention 188,381.84 180,406.84 5. Mobilization 9,000.00 9,000.00 6. Total Work Completed 121,497.84 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 197,381.84 189,406.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 189,406.84