Dept. of Trans. FINAL Serial No. Contract No. 11-230-13-44 04-1E4304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-84-R3.7/R27.1 Federal Project: 04-ALA-580-43.8/46.1 NONE 04-ALA-880-11.8/28.7 Progress payment No. 10 Payment period ending: 05-13-11 VICTORY ENGINEERS INC 10266 HIGHWAY 41 MADERA, CA 93636 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 211,397.86 3,750.00 2.a. Extra Work 51,573.57 0.00 b. Adjustment Comp. 14,341.36 0.00 3. Materials on Hand 4. Earned Subject to Retention 277,312.79 3,750.00 5. Mobilization 18,626.20 0.00 6. Total Work Completed 295,938.99 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 295,938.99 3,750.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,750.00