Dept. of Trans. PROGRESS Serial No. Contract No. 11-143-16-22 04-1E4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 84% 04-SCL-17-6.2/13.9 Federal Project: 04-SCL-35-R0.0/R0.0 NONE 04-SCL-85-3.5/R22.1 Progress payment No. 04 Payment period ending: 05-20-11 VICTORY ENGINEERS INC 10266 HIGHWAY 41 MADERA, CA 93636 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 566,932.02 52,059.33 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 566,932.02 52,059.33 5. Mobilization 32,047.17 0.00 6. Total Work Completed 598,979.19 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 598,979.19 52,059.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,059.33