Dept. of Trans. PROGRESS Serial No. Contract No. 10-236-16-18 04-1E6004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 37% 04-MRN-1-31.2/46.0 Federal Project: ACST-P001(547) P-P001(547) Progress payment No. 01 Payment period ending: 08-20-10 WINDSOR FUEL CO P O BOX 1029 PITTSBURG CA 94565 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 171,438.00 171,438.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 171,438.00 171,438.00 5. Mobilization 37,500.00 37,500.00 6. Total Work Completed 208,938.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 208,938.00 208,938.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 208,938.00